In April 2018, Dundas Street between Wellington and Ridout was a construction site. The city had just torn it up to build its first flex street: a curbless, shared corridor that could “seamlessly transition” from working road to civic plaza. The motto was unembarrassed, make Dundas Street the most exciting place in London. The budget was about $27 million (roughly $10M from the city, the rest riding along with utility work, since some of the sewers below dated to 1949).

Dundas Place opened in December 2019 with a final-brick ceremony. Then a pandemic emptied every downtown in North America for two years, about the harshest beta test a “most exciting place in London” could face. Here’s the honest scorecard.

What was promised

The original pitch, condensed: extra-wide sidewalks, no curbs, parking that flips into patios and pop-ups, and a street that closes to cars for festivals and concerts — Ottawa’s Sparks Street and Toronto’s Union Station plaza cited as the family tree — with the sewers and hydro below rebuilt while the surface got its makeover.

What got built

Physically: exactly that. The curbless design, the widened pedestrian zones, the convertible parking lane, the closable blocks — all delivered on the Wellington-to-Ridout footprint as drawn. As civic megaprojects go (and as our BRT and high-speed rail follow-ups document), delivered as designed is rarer than it should be. Dundas Place belongs on the short list of London projects that shipped.

What it became

The honest answer: an events platform that’s still growing into an everyday street.

When Dundas Place is programmed, the vision is fully visible — the street closes, the tents go up, and the corridor fills for concerts, pop-up markets, and food and cultural festivals. The current calendar is genuinely busy, with programming running through the summer (multiple event weekends across June, July, and August; the city maintains a public calendar at london.ca). The Colombian Gastronomy Festival, market weekends, and music programming have made the street the city’s default venue for anything too big for a sidewalk and too small for Victoria Park.

On an unprogrammed Tuesday, the street is quieter — and that’s the unfinished half of the project. A flex street is infrastructure; the daily life around it depends on the storefronts, the housing, and the foot traffic that downtown has been rebuilding post-pandemic. The towers rising nearby (see London’s Skyline Since 2018) are the slow-motion answer: every new resident within three blocks is a Dundas Place user the planners were counting on.

The verdict

Built as promised, used as promised on event days, still earning its weekdays. In the “What Got Built” standings, that puts Dundas Place comfortably ahead of the BRT’s compromises and high-speed rail’s vapour — a real thing, finished, that the city actually uses.

The most exciting place in London? On the right Saturday, honestly, yes.

Frequently asked questions

What is Dundas Place? London’s flex street: the curbless, shared stretch of Dundas Street between Wellington and Ridout downtown, designed to convert from a regular street to pedestrian event space. It opened in December 2019 after a roughly $27-million rebuild.

Is Dundas Place open to cars? Usually yes, it’s a shared street with priority for pedestrians and cyclists, and it closes fully to vehicles for festivals and events.

What events happen on Dundas Place? Concerts, pop-up markets, and food and cultural festivals through the warm months, with event weekends running from June through late August. The city posts the schedule on the Dundas Place calendar at london.ca.

How much did Dundas Place cost? About $27 million plus engineering, roughly $10 million from the city, with the balance tied to utility infrastructure replaced at the same time (some sewers below dated to 1949).

Was Dundas Place finished on time? Construction began in April 2018 with phase one targeted for that fall; the completed street officially opened in December 2019.