BRT Eight Years On: What London, Ontario Was Promised vs. What’s Actually Coming

· · 4 min read
BRT Eight Years On: What London, Ontario Was Promised vs. What's Actually Coming

Walk down King Street in downtown London, Ontario, past the Canada Life Place loading dock and you'll see them before you read the signs: the bus shelters that aren't quite like the others. Wider. Curved roof. A digital arrival board that actually works.

Walk down King Street in downtown London, Ontario, past the Canada Life Place loading dock and you’ll see them before you read the signs: the bus shelters that aren’t quite like the others. Wider. Curved roof. A digital arrival board that actually works. Those are the first finished pieces of London’s Bus Rapid Transit (BRT) system, and they’ve been carrying real passengers since late 2024.

This is what Bus Rapid Transit looks like in 2026: one operational segment, two corridors under construction, one corridor brought back from the dead, and a price tag nobody can publicly add up.

The promise

In March 2018, the City of London told residents to expect a Bus Rapid Transit system running by 2028. The price tag was $500 million. Two corridors: the first from Masonville to White Oaks on the north-south leg, the second Wonderland to Fanshawe College on the east-west, meeting at a downtown hub.

Council had just rejected a more ambitious $800 million light-rail and Bus Rapid Transit hybrid. BRT-only was the compromise: federal in for $200 million, province for $170 million, city on the hook for the remaining $130 million.

Yard signs went up across the affected neighbourhoods. “Up Shifts Creek,” the most organized opposition group, wrapped caution tape around trees that would be cut down. The original 2018 piece called it “controversial yet inevitable.”

Eight years later, “inevitable” turned out to be the right word. “By 2028” did not.

What’s actually built

As of mid-2026, exactly one piece of the system is moving buses: the Downtown Loop, which opened in late 2024. It covers King Street, Ontario Street, and part of Dundas, the spine that connects the two future legs through the city centre, running right past Covent Garden Market and the edge of Victoria Park. The first concrete BRT shelter went up in 2024. Buses use the dedicated lanes today.

That’s it. Everything else is under construction or in design.

What’s coming, with dates

The East London Link (what was the eastern half of the east-west route in the original 2018 plan) is the next leg to open. Completion scheduled for late 2026, operations start mid-2027, official opening targeted August 2027. It runs from downtown to Fanshawe College along Dundas Street and Oxford Street.

The Wellington Gateway, the southern half of the north-south corridor (downtown to White Oaks Mall), is further behind. Construction completes in 2027. Operations begin mid-2028. Public opening summer 2028.

A new project, the Highbury Bridge replacement (Phase 3B), is under construction through 2026. Phase 3A East, which covers Dundas Street from McCormick Boulevard to Highbury Avenue, is in construction now and slated for surface paving in 2028. Queen’s Bridge, the one-way westbound crossing of the Thames, started a transit-lane rehab in March 2026 that runs to May 2027.

The 2018 timeline said “between 2020 and 2028 the Bus Rapid Transit will be up and running for riders.” The current best case is summer 2028 for the southern leg, the eastern leg a year earlier. Two of the four originally-announced corridors will be partially open by the end of the original timeline. Two won’t.

The north leg story

The biggest plot twist isn’t the delays. It’s the north leg.

When council finalized the BRT plan, the northern route (Richmond Street up through Western University to Masonville Mall) was voted down. Western fought it hard. Several council members representing the affected wards joined the opposition. The federal funding earmarked for it got reallocated.

Then, in January 2026, the city quietly added it back. London’s 2026 budget submission to Queen’s Park asks the province for $100 million in capital funding to build the route the city previously rejected. The phrasing is that the north BRT leg “is receiving funding priority.” The Mobility Master Plan released in July 2025, which most Londoners did not read, identified the north leg, a west leg, and an additional north-south corridor as planning priorities.

So the north leg London voted down in 2019 may well be the next leg London builds. The city is not framing it as a reversal. It is one.

The money

The original $500 million estimate became approximately $454 million in committed funding by the early 2020s, but cost overruns have eaten into that number. In early 2026, capital money set aside to fix the Oxford-Wharncliffe intersection (a junction CBC London described in headline form as a “horror show”) was reallocated to cover BRT overruns. Federal and provincial budget asks now include the new north-leg funding request.

There is not, as of June 2026, a clean public number on the total all-in cost of the system. There likely won’t be one until the last leg is built.

What it changes for the rider

For now: not much. The Downtown Loop is the only operational piece, and most LTC buses through downtown were already using King and Dundas. The dedicated lanes speed up a handful of routes during peak hours.

By August 2027, riders coming from the east side of the city (Argyle, Pond Mills, the Fanshawe campus) will see the first real change. The eastbound corridor is the one with the strongest case in the 2018 piece: Fanshawe College students and Argyle commuters were the demographic that needed it most.

By summer 2028, White Oaks-to-downtown becomes BRT. South-end commuters get the second meaningful change.

The two corridors that aren’t built (the north leg through Western, and the west leg out toward Oxford and Wonderland) remain on paper. For now.

The honest read

In 2018, BRT was sold to Londoners as a single $500-million project running by the end of the decade. In 2026, it’s a phased multi-project program likely costing more than $500 million in total, with the first two legs opening in 2027 and 2028, the third still seeking funding, and the fourth in long-range planning.

The original yard-sign opposition aged interestingly. Some businesses on the affected routes did relocate. Some trees did come down. But the predicted “this will ruin our neighbourhood” outcomes have been hard to find, partly because most of the construction is still in progress, and partly because the city’s growth (Western enrolment, Fanshawe expansion, downtown towers) has continued regardless.

Whether BRT is the right answer for a city this size remains a debate. Whether it’s coming is no longer one.

London told its riders to be patient in 2018. The patient ones are still waiting.